Announcements

Office of the Mayor

CLEVELAND – On Wednesday April 17, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:
• East 47th Street – Southeast corner of St Clair Avenue and East 47th Street
• East 49th Street – Northwest corner of St Clair Avenue and East 49th Street

Read More

CLEVELAND – Beginning Wednesday, April 10, 2024, The City of Cleveland will restart construction of the South Moreland, Shaker Square, North Moreland Improvement Project, beginning in the southwest quadrant of Shaker Square.

Read More

CLEVELAND – During the week of April 15, 2024, weather permitting, the City will begin asphalt resurfacing on Bridge Avenue from West 50th Street to West 57th Street. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.
The project includes milling the existing asphalt pavement, adjusting utility castings, full depth pavement repairs, partial depth pavement repairs, replacement of curb, placement of compliant ADA ramps, placing new asphalt, and pavement markings. The work will take place during the hours of 7 a.m. to 5 p.m. The asphalt resurfacing project is expected to complete by the end of June 2024.

Read More

CLEVELAND – During the week of April 18, 2024, weather permitting, the City will begin asphalt resurfacing on Dick Goddard Way from East 55th Street to East End. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.
The project includes milling the existing asphalt pavement, adjusting utility castings, full depth pavement repairs, partial depth pavement repairs, replacement of curb, placement of compliant ADA ramps, placing new asphalt, and pavement markings. The work will take place during the hours of 7 a.m. to 5 p.m. The asphalt resurfacing project is expected to complete by the end of June 2024.

Read More

CLEVELAND – Beginning April 19, 2024, weather permitting, the City will begin asphalt resurfacing on North Marginal Road from East 55th Street to Martin Luther
King Jr. Drive. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street
parking will be permitted for the duration of the project.
The project includes milling the existing concrete pavement, adjusting utility castings, partial depth pavement repairs, placement of compliant ADA ramps, placing new
asphalt, and pavement markings. The work will take place during the hours of 7 a.m. to 5 p.m. The resurfacing project is expected to complete by the end of June 2024.

Read More

CLEVELAND – During the week of April 17, 2024, weather permitting, the City will begin asphalt resurfacing on Wade Avenue from West End to West 25th Street. A portion of the street will be closed, and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.
The project includes milling the existing asphalt pavement, adjusting utility castings, full depth pavement repairs, partial depth pavement repairs, replacement of curb, placement of compliant ADA ramps, placing new asphalt, and pavement markings. The work will take place during the hours of 7 a.m. to 5 p.m. The asphalt resurfacing project is expected to complete by the end of June 2024.

Read More

CLEVELAND – During the week of April 9, 2024, weather permitting, the City will begin brick restoration of Othello Avenue from Mcelhattan Avenue to East 140th Street. A complete closure is not expected to occur is not expected to occur, local access will be maintained. No on-street parking will be permitted for the duration of the project.
The project will remove and reset sunken bricks within the street. The work will take place during the hours of 7 a.m. to 5 p.m. The brick restoration project is expected to complete by the end of June 2024.

Read More

CLEVELAND – Beginning April 16, 2024, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 3. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be complete by the end of June 2024:
• Train Avenue (Richner Avenue to Vega Avenue)
One lane of traffic will be maintained for local traffic for the duration of each project. No detours are expected. Access to all businesses, residences and side streets will be maintained during construction. On-street parking will not be allowed during construction. The work will take place during the hours of 7 a.m. to 5 p.m.

Read More

CLEVELAND – Beginning April 12, 2024, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 15. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be complete by the end of June 2024:
• Train Court (Train Avenue to West 56th Street)
• Herman Avenue (West 58th Street to West 49th Street)
• West 98th Street (Madison Avenue to Cudell Avenue)
• West 93rd Street (Madison Avenue to North End)
One lane of traffic will be maintained for local traffic for the duration of each project. No detours are expected. Access to all businesses, residences and side streets will be maintained during construction. On-street parking will not be allowed during construction. The work will take place during the hours of 7 a.m. to 5 p.m.

Read More

CLEVELAND – Beginning April 15, 2024, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 15. Advance notice signs will be posted to advise the public of road improvements. The following streets will be complete by the end of June 2024:
• Mirlo Court (West 67th Street to Approximately 300’ West of West 67th Street)
One lane of traffic will be maintained for local traffic for the duration of each project. No detours are expected. Access to all businesses, residences and side streets will be maintained during construction. On-street parking will not be allowed during construction. The work will take place during the hours of 7 a.m. to 5 p.m.

Read More

CLEVELAND – Beginning April 9, 2024, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 16. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be complete by the end of June 2024:
• West 148th Street (Justin Avenue to Puritas Avenue)
• Tyler Avenue (West 140th Street to Victory Boulevard)
• West 133rd Street (Lorain Avenue to West Avenue)
One lane of traffic will be maintained for local traffic for the duration of each project. No detours are expected. Access to all businesses, residences and side streets will be maintained during construction. On-street parking will not be allowed during construction. The work will take place during the hours of 7 a.m. to 5 p.m.

Read More

Invite you to an Open House Presentation for the Superior Midway Project (East Roadway to East 55th Street). Important information about the ongoing, preliminary design will be presented. Design will be completed in spring 2025 and construction is scheduled to begin in fall 2025.
When: Thursday, April 25, 2024 at 6:00 pm
Where: Goldhorn Brewery, 1361 East 55th Street, Cleveland, Ohio 44103

More

The Urban Forestry Commission will host its next virtual Budget Committee Hearing on Tuesday, March 19, 2024 from 3pm-4pm. The public is welcome to join via WebEx. Recordings will be posted to Sustainable Cleveland's YouTube channel.

Meeting WebEX: https://us02web.zoom.us/j/81906591197?pwd=RkJvSXFKbXVJQnFRREs0ODlCME1od…

CLEVELAND – Recently, the City resumed construction of Phase 2 of the East 79th Street Rehabilitation Project from Cedar Avenue to Chester Avenue and south of Woodland Avenue under Norfolk Southern Railroad Bridge.

Effective Monday, March 18, 2024, weather permitting, the City of Cleveland will close traffic south of Woodland Avenue underneath the railroad bridge The traffic pattern between Cedar Avenue and Chester Avenue is not expected to change.

Read More

CLEVELAND – On Monday March 18, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:
• Lee Road – From Sunny Glen Avenue to Seville Road
The improvements include replacing the old steel mainline with a new plastic mainline in the roadway and sidewalk area. A work zone will be established which will allow two-way traffic with traffic control personnel present to help direct traffic flow. Access to adjacent driveways and businesses will be maintained throughout construction. The work on the project will take place Monday through Friday from 7 a.m. to 5 p.m.
This project is scheduled for completion in May 2024. Permanent restorations will be completed in July 2024.

Read More

CLEVELAND – On Monday, March 25, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:
• Denison Avenue – From West 59 Street to West 69 Street
• West 69 Street – East side from Denison Avenue to 3567 West 69 Street
• West 67 Street – From Denison Avenue to Barberton Avenue.
• West 66 Street – West side from Denison Avenue to Barberton Avenue.
• West 59 Street – West side from Denison Avenue to Storer Avenue.
• West 58 Street – West side from Denison Avenue to Rail Road Tracks

Read More

The Board of Revision of Assessments (“Board”) has scheduled a meeting to hear objections to the following street vacation resolution:

  • Resolution No. 517-2023 – To vacate a portion of Curtis Avenue N.E., east of East 59th Street.

The Board has scheduled its meeting for March 14, 2024, at 1:30 p.m, in Room 514, City Hall, 601 Lakeside Avenue, Cleveland, OH 44114. Your attendance at this meeting is optional, unless you are opposed to the proposed vacation, or there are City of Cleveland Departmental charges involved.

If you have questions regarding this notification, please email or call (216) 664-3875, Monday-Friday between 8:00 a.m. and 4:30 p.m.

CLEVELAND – On Monday, March 4, 2024, Dominion Energy Ohio’s Gas pipeline infrastructure replacement project will begin on the following street:
• Bailey Avenue – North side from West 41st Street to 4200 Bailey Avenue
The improvements include replacing the old steel mainline with a new plastic mainline in the roadway and sidewalk area. As well as the removal of the old underground vault system. A work zone will be established which will allow two-way traffic with traffic control personnel present to help direct traffic flow. Access to adjacent driveways and businesses will be maintained throughout construction. The work on the project will take place Monday through Friday from 9 a.m. to 4 p.m.
Work has and will continue to be coordinated with the Orchard STEM School.

Read More

When: March 7, 2024 at 5:00 pm
Where: PNC Fairfax Connection, 8220 Carnegie Avenue, Cleveland, Ohio 44103
What: To provide information regarding the Design of the Carnegie Avenue Rehabilitation project. Final Design is scheduled to be completed in June 2024. Construction is scheduled to begin March 2025.

Read More

CLEVELAND – On Monday, February 19, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:
• Fenwick Avenue – North side from South Frontage Road to West 47 Street
• Walworth Avenue – 5601 Walworth Avenue to Junction Road
• Train Avenue – Train Court to West 46 Street
• West 53 Street – Train Avenue to Clark Avenue
• West 51 Street – West Side Train Avenue to Clark Avenue
• West 47 Street – West Side Train Avenue to Clark Avenue and East side from Ravine      Court to Fenwick Avenue.
• West 45 Street – East side from Ravine Court to Fenwick Avenue.

Read More

CLEVELAND – Beginning Thursday, February 22, 2024, weather permitting, the City of Cleveland will begin construction of Phase 2 of the East 79th Street Rehabilitation Project from Cedar Avenue to Chester Avenue and south of Woodland under the Norfolk Southern Railroad Bridge.

Read More

Applications for summer youth employment are now being accepted through May 1st, 2024.

2024 Summer Jobs Flyer

2024 Summer Jobs Flyer (Spanish)

CLEVELAND – On Monday, February 19, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:

  • Fenwick Avenue – North side from South Frontage Road to West 47 Street
  • Walworth Avenue – 5601 Walworth Avenue to Junction Road
  • Train Avenue – Train Court to West 46 Street
  • West 53 Street – Train Avenue to Clark Avenue
  • West 51 Street – West Side Train Avenue to Clark Avenue
  • West 47 Street – West Side Train Avenue to Clark Avenue and East side from Ravine Court to Fenwick Avenue
  • West 45 Street – East side from Ravine Court to Fenwick Avenue

Read More

CLEVELAND – On Monday, February 05, 2024, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:
• Bessemer Avenue – From East 79th Street to 7424 Bessemer Avenue
The improvements include replacing the old steel mainline with a new plastic mainline in the roadway and sidewalk area. A work zone will be established which will allow two-way traffic with traffic control personnel present to help direct traffic flow. Access to adjacent driveways and businesses will be maintained throughout construction. The work on the project will take place Monday through Friday from 7 a.m. to 5 p.m.
This project is scheduled for completion in April 2024. Should the weather not allow for permanent restoration to the sidewalk and roadway after construction. A temporary 2” thick concrete sidewalk will be installed for pedestrian traffic, and concrete road caps will be placed on all road crossings until permanent restorations can be completed in the Spring 2024.

Read More

CLEVELAND – On January 8, 2024 until January 23, 2024, Carter Road will be closed to through traffic between the Carter Road Lift Bridge and Columbus Road.  Carter Road must be closed to traffic to safely finish utility work tie-ins.
Vehicle and pedestrian traffic will be detoured along Columbus Road – detour signs will be in place.  During the work, traffic and pedestrian access may be temporarily restricted or delayed due to the contractor’s operations.
Motorist should be alert for traffic signage used to direct traffic at the designated repair work sites.
Should there be any questions, please contact the project manager, Mr. Mike Waina at 440-994-0563.

Read More

Get paid to work poolside! Lifeguard Training and Placement: Six upcoming classes starting December 18th.

Lifeguard Flyer - 2023 - Winter Classes

Programs and services are available across the city’s 22 Neighborhood Resource & Recreation Centers. Opportunities in STEM, the arts, workforce training, fitness, and more are available.

Winter 2023-24 Programs Registration Form

CLEVELAND – The Eagle Avenue Lift Bridge is scheduled for demolition between July 2024 and May 2025 with the principal work proceeding through the winter into spring. There will be impact to traffic on the Ohio & Erie Towpath Trail alongside Scranton Road and at the intersection with Carter Road at various times during that timeframe to protect the public.

2023-11-28 Eagle Avenue Bridge Public Notice - 4(f) De Minmis

CLEVELAND – Beginning November 15, 2023, weather permitting, the City will begin concrete roadway construction on West 20th Place from the North End to approximately 50’ north of Smith Court. There will be no access to West 20th Place from Smith Court for the duration of the project. No on-street parking will be permitted for the duration of the project.
The project includes removing the existing gravel roadway and placing concrete pavement. The work will take place during the hours of 7 a.m. to 5 p.m. The concrete roadway construction project is expected to complete by December 15, 2023, weather permitting.

11-10-2023_TRAFFIC Advisory West 20th Place

CLEVELAND – Beginning Saturday November 11, 2023, Huron will be closed to through traffic from Ontario to Prospect. Huron will reopen on November 14 2023.  The closure is necessary for the demolition of the 611 Huron Parking Structure.

11-10-2023 Huron Road Traffic Advisory

CLEVELAND – Beginning Monday, November 6, 2023, the Ohio Department of Transportation, through its contractor, will be con-ducting work on the Center Street Swing Bridge as part of the re-habilitation project. There will be two closures:
•    Monday, November 6th – 9 a.m. to 12 p.m.
•    Tuesday November 7th – 9 a.m. to 12 p.m.

Read More

Veterans Resource Fair
When: Tuesday, November 8, 2023, 11:00 am - 2:00 pm
Where: Frederick Douglass Rec. Center, 15401 Miles Avenue, Cleveland

More

Invite you to an Open House Presentation for the Superior Midway Project (East Roadway to East 55 Street). Important information about the ongoing, preliminary design will be presented. Design will be completed in late 2024 and construction is scheduled to begin in 2025.
When: Tuesday, November 14, 2023 at 6:00 pm
Where: Red Space, 2400 Superior Avenue, Cleveland Ohio 44114

More

CLEVELAND – Beginning Monday, October 23, 2023, the Ohio Department of Transportation will be conducting work on the Center Street Swing Bridge as part of the rehabilitation project. There will be four closures for testing purposes which will be as follows:

•    Monday. October 23rd (7pm – 6 am)
•    Tuesday, October 24th (7 pm - 6 am) 
•    Tuesday, October 24th (9 am - 11 am) 
•    Wednesday, October 25th (9 am - 12 pm)

Read More

Important information about the ongoing preliminary design will be presented. The design will be completed in late 2024 and construction is scheduled to begin in 2025.

Accouncement

Stakeholder Meeting Invite Letter

Beginning September 27, 2023, weather permitting, the City will start Phase 2 concrete repairs on Rocky River Drive from Lorain Avenue to McKinley Avenue. A portion of the street will be closed, and one lane of traffic will be maintained northbound. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project in the affected areas and no parking signs will be posted. 

Phase 1 was completed in the winter of 2021-2022 from Munn Road south to Lorain Road. Phase 2 consists of concrete repairs from Munn Road north to McKinley Avenue and is expected to last approximately 8 weeks, weather permitting.

Read More

Revere Avenue, East 139th Street, East 118th Street, Glendale Avenue Beginning September 29, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 2. Advance notice signs will be posted to advise the public of road improvements.

Read More

East 139th Street, East 98th Street, Dickens Avenue, Revere Avenue Beginning September 29, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 4. Advance notice signs will be posted to advise the public of road improvements.

Read More

Beginning September 26, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 12. Advance notice signs will be posted to advise the public of road improvements.

Read More

To provide feedback from questions/comments asked at the first Design Public Meeting, which occurred on May 10, 2023

2023-09-20 Design2 Public Meeting Carnegie Part 1 Flyer

Beginning Monday, September 18, 2023, weather permitting, Fairmount Properties will begin construction on the East 105th Street Median Removal and Left Turn Lane at Frank Avenue construction project.

E 105 Median Cut Traffic Advisory

Beginning Monday, September 25, 2023, weather permitting, the City of Cleveland will begin the construction of Phase 2 of the East 79th Street Rehabilitation Project which extends from Cedar Avenue to Chester Avenue.

East 79th Traffic Advisory

Effective Friday morning, September 15th, at 6:00 a.m., Euclid Ave. will be closed between E. 6th St. and E. 9th St. for the removal of a tower crane at the City Club Apartments. A detour will be posted. Euclid Ave. will reopen on Monday, September 18th, at 6:00 a.m.

09-15-23 Euclid Ave. Traffic Advisory

Get paid to work poolside! Lifeguard Training and Placement: two upcoming classes starting September 18th.

Lifeguard Flyer - 2023 - Fall Classes

Beginning Thursday, September 14, 2023, the City of Cleveland will inspect the Willow Avenue Lift Bridge located north of the Elm Street and River Road in-tersection to Whiskey Island Drive. The inspection is for one day and will begin at 7 a.m. and end at 5 p.m

Important information about the upcoming construction project will be presented. Construction is currently scheduled to begin in July 2024 and to be completed by December 2024.

September 5th at 4:00 pm 

Online Click here to join the meeting

Meeting ID: 253 846 491 314 

Passcode: pbJFQr 

Or call in (audio only) +1 216-306-2628 

Phone Conference ID: 969 276 005#

Beginning September 15, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 11. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be complete by the end of October 2023: 

  • West 122nd Street (Wanda Avenue to Sobieski Avenue) 
  • West 98th Street (Almira Avenue to Loretta Avenue) 
  • West 99th Street (Almira Avenue to Walford Avenue) 
  • West 110th Street (Almira Avenue to Florian Avenue) 
  • Bosworth Road (Bellaire Road to Briggs Road) 
  • West 127th Street (Kadel Avenue to Leeila Avenue) 
  • South Frontage (West 106th Street to West 103rd Street) 
  • Maywood Avenue (West 88th Street to West 97th Street)

Beginning Thursday, August 31, 2023, the City of Cleveland will inspect the Carter Road Lift Bridge located north of the Carter Road and south of Columbus Road. The inspection is for one day and will occur between 7 a.m. and 5 p.m.

More

Beginning August 31, 2023, weather permitting, the City will begin asphalt resurfacing on Hickory Court from East 12th Street to West End. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.

More

Beginning August 31, 2023, weather permitting, the City will begin asphalt resurfacing on East 12th Street from Euclid Avenue to Chester Avenue. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.

More

Beginning August 22nd, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 14. Advance notice signs will be posted to advise the public of road improvements. The following streets will be complete by the end of October 2023: Trent Avenue (Fulton Road to West 38th Street); Daisy Avenue (West 32nd Street to West 39th Place); West 32nd Street (Marvin Avenue to Daisy Avenue); West 88th Street (Denison Avenue to Brinsmade Avenue); Kouba Avenue (West 48th Street to West 56th Street). 

More

Beginning August 22, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 17. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be completed in mid-October: Montrose Avenue (Glencliffe Road to Warren Road); Riveredge Road (Larchwood Avenue to End); Old Lorain Road (Lorain Avenue to Valley Parkway); West 183th Street (Puritas Avenue to Ponciana Avenue). 

More

Beginning August 23, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 15. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be completed in mid-October: West 115th Street (Lake Avenue to Harborview Drive); West 89th Street (Madison Avenue to Sauer Avenue); West 85th Street (Madison Avenue to Willard Avenue); Scott Court (West 57th Street to Dead End); Ellen Avenue (West 58th Street to West 65th Street); Mirlo Court (West 67th Street to Approximately 300’ West of West 67th Street). 

More

Beginning August 25, 2023, weather permitting, the City of Cleveland’s Back to Basics Street Improvement Program, funded by the American Rescue Plan Act (ARPA) will begin in Ward 3. Advance notice signs will be posted to advise the public of road improvements. The following streets are expected to be completed in mid-October: Erin Avenue (West 38th Street to West 32nd Street); Train Avenue (Richner Avenue to Vega Avenue); Center Street (Center Street Swing Bridge to Robert Lockwood Junior Drive); Center Street (River Road to Center Street Swing Bridge). 

More

Beginning August 7th, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 11. Advance notice signs will be posted to advise the public of road improvements. Affected streets include West 94th Street, West 97th Street, Brookfield Avenue, Jasper Road, and Kensington Avenue. Work is expected to be completed by the end of September 2023.

More

On Wednesday, August 9, 2023, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets: Lee Road (from McCracken Road to Seville Road), Seville Road (from Lee Road to 16306 Seville Road), and Myrtle Avenue (from Lee Road to 16304 Myrtle Avenue. This project is scheduled for completion in November 2023.

More

On Monday, July 31, 2023, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets: Eliot Avenue (South side from East 102nd Street to East 110th Street), East 102 Street (from Marah Avenue to Heath Avenue), and Raymond Avenue (North side from East 93rd Street to East 102nd Street). This project is scheduled for completion in September 2023. Permanent restorations will be completed in October 2023.

More

Beginning July 25th, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 1. Advance notice signs will be posted to advise the public of road improvements. Affected streets include Alonzo Avenue, Strandhill Road, Glendale Avenue, and Woda Avenue. Work is expected to be completed by the end of September 2023.

More

The Board of Revision of Assessments (“Board”) has scheduled a meeting to hear objections to the following street vacation resolution:

  • Resolution No. 44-2023 – To vacate all of East 59th Street, from Central Avenue to Hawthorne Avenue and all of Hawthorne Court, from East 59th Street to East 61st Street.

The Board has scheduled its meeting for August 24, 2023, at 1:30 p.m, in Room 514, City Hall, 601 Lakeside Avenue, Cleveland, OH 44114. Your attendance at this meeting is optional, unless you are opposed to the proposed vacation, or there are City of Cleveland Departmental charges involved.

If you have questions regarding this notification, please email or call (216) 664-3875, Monday-Friday between 8:00 a.m. and 4:30 p.m.

The City of Cleveland, in partnership with the Ohio Department of Transportation (ODOT), would like to invite the public to participate in a virtual open house to learn more about the proposed project to remove the Eagle Avenue Bridge over the Cuyahoga River in Cleveland. Due to its poor physical condition and increasingly rapid deterioration, the City of Cleveland has determined that removing the existing bridge is the safest and most cost-effective alternative that satisfies the purpose of the project.

More

The City of Cleveland’s budget is one of the most important documents that the City prepares as it identifies the services to be provided and how they will be financed. This document is designed to assist the reader in understanding the City’s budgetary processes and resultant budgets. It includes a 3 year historical budgetary line item of expenses and revenue, as well as detailed staffing levels for every department.

More

Beginning July 26th, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 4. Advance notice signs will be posted to advise the public of road improvements. Affected streets include East 123rd Street, East 129th Street, East 128th Street, Parkview Avenue, East 113th Street, and Kolar Avenue. Work is expected to be completed by the end of August 2023. 

More

Beginning, Monday July 10th, The Perk Company will close Franklin Blvd. at the intersections of West 48th Street and West 38th Street. The West 45th street intersection will remain open to all traffic. 

More

Beginning July 12, 2023, weather permitting, the City will begin asphalt resurfacing on East 123rd Street from Superior Avenue to Durant Avenue. A portion of the street will be closed and one lane of traffic will be maintained in each direction. A complete closure is not expected to occur. No on-street parking will be permitted for the duration of the project.

More

Beginning June 26th, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 2. Affected streets include Effie Road, East 106th Street, East 112th Street, East 119th Street, Beachwood Avenue, and East 144th.

More

On Thursday, July 6, 2023, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin in parts of Ward 10. The project is scheduled for completion in September 2023. Streets impacted include East 146 Street, East 147 Street, Galewood Drive, and Ingalton Avenue. 

More

On Monday June 26, 2023, weather permitting, the ODOT’s contractor will begin mobilizing and establishing traffic controls on Euclid Avenue from Ivanhoe Road to Upper Valley Drive. Resurfacing of approximately 1.24 miles of Euclid Ave. from Ivanhoe Road / West Belvoir Blvd. to Upper Valley Drive is scheduled to be completed in November 2023. 

More

On Wednesday, July 5, 2023, Dominion Energy Ohio’s gas pipeline infrastructure replacement project will begin on the following streets:

  • Saint Clair Avenue – South Side from East 64 Street to East 69th Street
  • Addison Avenue – From Saint Clair Avenue to Superior Avenue
  • Bayliss Avenue – North side from East 67 Street to Addison Avenue
  • Hecker Avenue – North side from East 71 Street to Addison Avenue
  • Bliss Avenue – From Saint Clair Avenue to East 71 St
  • East 66 Street – From Saint Clair Avenue to Bliss Avenue
  • East 67 Street – From Saint Clair Avenue to Bliss Avenue

More

Beginning June 28th, 2023, weather permitting, the City of Cleveland’s Residential Resurfacing Program will continue in Ward 3. Advance notice signs will be posted to advise the public of road improvements.

More

We are very pleased to announce the City of Cleveland has finalized the roll-out of the 2023 Community Choice Electricity Aggregation to our eligible residents and small commercial businesses, starting in August 2023, thanks to City Council’s timely legislative approvals and work by our program partner Sustainable Ohio Public Energy Council - SOPEC. Through our group buying power with selected aggregator SOPEC, the city administration was able to secure a very competitive default ‘opt-out’ 1 year fixed rate of 6.302 cents/kWh for the electricity supply, backed by 100% Green-e certified Renewable Energy Credits (RECs).  This price will save the average residential electricity account approximately $200 over the next year, compared to the Illuminating Company’s default electricity supply rates (12.4 cent/kWh). As early as Tuesday, June 20th, eligible Cleveland residents can expect to see letters from SOPEC that outline the community choice aggregation program, including “opt-out” pathways. For questions related to the program, contact SOPEC at 1877-648-1937 If you are a low-income household experiencing high energy burdens, we encourage you to enroll into utility assistance programs. Please contact either CHN Housing Partners or Step Forward for information at 216-350-8008
For more information and the latest updates, please visit SustainableCleveland.org/CommunityChoiceAggregation

Starting April 24, 2023, W. 3rd Street will be fully closed to vehicular and pedestrian traffic between Superior Avenue and Frankfort Avenue until November 2024 due to the construction of the Sherwin Williams Headquarters. Signage detailing detours will be in place at that time. Please expect delays in this area.

More

Beginning Monday, May 8, 2023, weather permitting, ODOT will begin construction of Stage 1 work on East 140th Street between St. Clair Avenue and Aspinwall Avenue. 

More

Beginning Monday, April 3, 2023, weather permitting, the City of Cleveland will begin the construction of Phase 2 of the West Franklin Boulevard Rehabilitation Project from West 50th Street to West 25th Street.

More

The Division of Recreation is now hiring for multiple open positions, including counselors, student aides, recreation instructors, and more. Call 216-664-2325 for more info, or apply online.

More

Beginning Wednesday, March 22, 2023, weather permitting, ODOT will begin construction of Phase 2 work on East 185th Street between Nottingham Road and Pawnee Avenue. 

More

Beginning Monday, March 13, 2023, The City of Cleveland will begin the East 79th Street Rehabilitation Project from Woodland Avenue to Chester Avenue. The project includes resurfacing of 1.28 miles of East 79th St from Woodland Ave. to Chester Ave.

More

The Board of Control will meet in person on Wednesday, August 2, 2023, in the Mayor's Office Red Room, Room 202, 2nd Floor, City Hall. Upon entry to Room 202, the Red Room is the first door on the left.

The current agenda is available here. Meeting minutes are published in the City Record.

Under the conditions specified by law, a WebEx session will be used to facilitate and record the meetings and the meetings will be live streamed on YouTube.

Anyone wishing to address the Board on any agenda item may do so with the permission of the Board, but in no case, shall the address exceed five minutes in duration unless additional time is allowed by the Board. We ask individuals who wish to address the Board on an agenda item to contact the Department of Law by email or phone (email is preferred). Individuals not seeking to address the Board during the WebEx session are encouraged to view one of the live streams.

If you wish to attend or participate virtually in the Board of Control meeting, please send a request by email, no later than 12:00 noon Wednesday, to Alberto Guzman, copy(CC) to Jeffrey Marks, Tiffany Fischbach, Vishnu Ganglani, Patricia Aston, and Jason Shachner.

More